Load test
Phase of a project in which the installation is subjected to real operation before acceptance. It concentrates a large part of the claims during the period.
In practice
The all-risk construction limits its duration —often four weeks— and for used equipment usually excludes it. In industrial projects, it is advisable to negotiate it before setting the commissioning schedule.
Where it is addressed
This term is covered in Construcción y obra and applies when taking out Construcción.